Your risk manager asks for the HTM department's top five risks by the end of the week, for a report going to the board. You have incident reports, a service history, a recall folder, and a backlog list, and none of them is labeled "risk". Turning what you already know into five ranked statements somebody else can act on is the whole job of this lesson.

The five categories, with an HTM example of each

Category                 What it looks like in your department
Patient safety           a device that shocks, burns, delivers the wrong dose, or
                         reads out of calibration and leads to a misdiagnosis
Operations               downtime on the only device of its kind, a canceled
                         procedure, a surgeon who takes cases elsewhere
Financial                unplanned repairs that break the budget, a contract
                         signed without review, a fine, the cost of a lawsuit
Emergency preparedness   a utility or network failure that leaves clinicians
                         without working equipment and no written workaround
Regulatory               a survey finding on maintenance records, an unreported
                         adverse event, equipment in an alternative maintenance
                         program that was never eligible for it

They overlap on purpose. One failed sterilizer is a patient safety risk, an operations risk, a financial risk, and a regulatory risk at the same time, and naming all four is what gets it funded.

Risk is likelihood and consequence

A risk statement that names only the bad outcome cannot be ranked. Every risk has two dimensions: how likely it is, from your own history or credible outside data, and how bad it is if it happens. A rare event with catastrophic consequence and a weekly event with a trivial consequence can carry the same score and need completely different responses. Write each risk as a sentence that holds both: if this happens, that follows, and here is how often we have seen it.

There is a trade behind every decision you will make with these numbers. Risk and cost move in opposite directions. Almost any risk can be driven close to zero if the hospital spends enough, and cost comes down only by accepting more risk. The hospital's risk management department decides how much risk is acceptable; your job is to state the risk honestly and price the options.

Where the information comes from

  • Incident reports from the hospital's event system, including the ones that never mention a device by name.
  • Service history in the CMMS: repeat repairs, use error codes, cannot-duplicate calls, rising failure rates.
  • Recalls and advisories received and still open.
  • Survey findings from your accreditor and from internal audits.
  • Staff rounds in the clinical units, which surface the workaround nobody reported.
  • Near misses, which are the cheapest data you will ever get and the most often thrown away.

The risk register

A risk register is one list, maintained rather than written once. Each entry holds the risk statement, the category, the likelihood and consequence, the current score, the controls already in place, the named owner, the action with a date, and the review date. It is the document the risk manager actually wants, and it is what lets you answer "what are your top five" in one minute rather than one week.

Who owns what, and when you escalate

Ownership follows the ability to act. HTM owns equipment condition, maintenance strategy, recall execution, and technical advice. The clinical department owns operator competence, device use, and reporting events. IT and the security officer own network and security controls jointly with you. Facilities own power, gases, water, and ventilation. Risk management owns the hospital's tolerance and the investigation. Escalate the moment a risk is beyond your authority or your budget to control, when a device has harmed a patient, when a recall is a Class I, or when a control you recommended has been refused. Escalate in writing, name what you recommended, and keep the copy.

Exam tip: the five categories are patient safety, operations, financial, emergency preparedness, and regulatory. Risk is likelihood times consequence, risk and cost move in opposite directions, and the hospital's risk management department sets what is acceptable. The risk register is the document that holds it all with a named owner per line.
Remember
Risk comes in five categories, is stated as likelihood and consequence rather than outcome alone, is collected from incidents, service history, recalls, surveys, rounds, and near misses, and lives in a risk register with a named owner on every line.
Deeper explanation

Identifying and Evaluating Risk: Patient Safety, Operations, Financial, Emergency Preparedness, Regulatory, explained slowly

A risk register page, as a risk manager wants to receive it

Five entries from a real department, scored on a 1 to 5 scale for likelihood and consequence, with the product as the score.

#  Risk statement                      Category      L  C  Score  Owner
1  The single sterilizer in the main   patient       4  5     20  HTM manager
   OR fails and cases are canceled;    safety and             with surgical
   it has failed twice this year        operations             services
2  Eleven legacy monitors run an       regulatory    3  5     15  HTM manager
   operating system no longer           and patient            with the
   supported; they cannot be patched    safety                 security officer
3  Infusion pumps on three units are   patient       3  4     12  clinical
   programmed without the drug          safety                 director,
   library because staff bypass it                             nursing
4  No documented downtime procedure    emergency     2  5     10  HTM manager
   exists for the imaging archive       preparedness           with IT
5  Scheduled maintenance backlog has   regulatory    4  2      8  HTM manager
   grown for three quarters
#  Controls already in place             Action, owner, date
1  quarterly scheduled maintenance;     capital request for a second unit
   a loaner agreement with a nearby     submitted; interim written transfer
   hospital                             agreement signed; HTM, by 30 June
2  on a separate network segment;       replacement in the three-year capital
   no internet reachability             plan; compensating controls documented
                                        and accepted; HTM and security, by
                                        31 March
3  library installed; training          observation audit on all three units,
   delivered at install                  then in-service on every shift;
                                        nursing education, by 15 May
4  none                                 downtime procedure drafted and tested
                                        in the next drill; HTM with IT, by
                                        31 July
5  weekly backlog review                staffing analysis attached to the
                                        budget request; HTM, by 1 September

Everything a manager needs to answer "what are your top five" is on those two pages, and every line has a name and a date on it. A register without owners and dates is a list of complaints.

Likelihood and consequence, and why both are required

Risk                            Likelihood  Consequence  Score  Response
Exam light bulb fails               5            1          5   spares on the cart
A defibrillator fails to            1            5          5   test it, every time,
deliver on a code                                               and never run to
                                                                failure

Identical scores, opposite responses. That is why a score ranks work but never replaces judgment, and why the severity dimension gets read on its own before any ranked list is accepted.

Reading your own data for risk

Source                 What to pull                    What it reveals
Incident reports       every event where a device was   events your shop never
                       present, device named or not     heard about
CMMS service history   repeat repairs within 30 days,   a bad model, a bad part,
                       use error codes, cannot-         or a training gap
                       duplicate calls
Recall and advisory    open notices, and the age of     a compliance exposure
log                    the oldest
Survey findings        every finding touching           where the accreditor
                       equipment, internal or external  already told you
Staff rounds           the workaround nobody reported   the risk that is invisible
                                                        in every database
Near misses            the events that did not reach    the cheapest data you
                       a patient                        will ever get

Ownership and escalation

Risk area                               Owner                  HTM's part
Equipment condition and maintenance     HTM                    all of it
strategy
Operator competence and device use      clinical department     measure and report
                                                                use error trends
Network and security controls           IT and the security     joint; inventory,
                                        officer                 MDS2, and the
                                                                device knowledge
Power, gases, water, ventilation        facilities              which devices
                                                                depend on each
Hospital risk tolerance and the         risk management         state the risk and
investigation                                                   price the options

Escalate immediately when
  a device has harmed a patient
  a Class I recall names equipment you own
  a control you recommended has been refused
  the risk exceeds your authority or your budget to control
Escalate in writing, name what you recommended, keep the copy.

What to memorize

Five categories   patient safety, operations, financial, emergency
                  preparedness, regulatory
Risk              likelihood and consequence, both stated
The trade         risk and cost move in opposite directions; risk management
                  decides what is acceptable
Sources           incident reports, service history, recalls, surveys, staff
                  rounds, near misses
Register          statement, category, likelihood, consequence, score,
                  controls, owner, action, date, review date